With the end of the year getting closer, it's time to talk the yearly update!

As previously stated, this years the project decided to apply different changes to the procedure, allowing design updates even for slim books!

How are things going?

Well, in general, the procedure was as follows:

- ACS investigated with community which were the problems, and prioritised them
- ACS and External Experts presented problems to RT
- RT sorted out which ones to send to GDT for redesign/simplification, and which ones can be fixed with points only
- GDT prepaired several proposals
- RT picked the ones which seemed to address best the issues
- the ones picked were then sent to ACS, GDT and BGT for review.
- Those clearly disliked were sent back to be redesigned again, for another cycle
- GDT and RT priced all the changes
- when all had converged to a solution, RT sent changes to RCT

More in particular, we divided the update in 3 batches, with this in mind:







ActionsBatch 1 datesBatch 2 datesBatch 3 dates
LAB teamsRedesign delivered to RTDeadline for changes Oct 03--
RTDesign and price changes completedDeadline for changes Oct 17Deadline for changes Nov 01Deadline for changes Nov 15
BGTNew names for new designsChanges delivered Oct 18
- 1 week to work, deliver new names to RT
Changes delivered Nov 02
- 1 week to work, deliver new names to RT
Changes delivered Nov 16
- 1 week to work, deliver new names to RT
RCTDesign changes are turned into exact wording Changes delivered Oct 18 without new names,Oct 25 with new names
- 1(2) weeks to work, then deliver to layout
Changes delivered Nov 02 without new names,Nov 09 with new names
- 1(2) weeks to work, then deliver to layout
Changes delivered Nov 16 without new names,Nov 23 with new names
- 1(2) weeks to work, then deliver to layout
LayoutImplements text from RCT in latex templates Changes delivered Nov 02
- 2 weeks to work, then deliver to translation and tool support
Changes delivered Nov 16
- 2 weeks to work, then deliver to translation and tool support
Changes delivered Nov 30
- 2 weeks to work, then deliver to translation and tool support
Transl.Update non English booksBooks delivered Nov 16
- 1 week to work
Books delivered Nov 30
- 1 week to work
Books delivered Dec 14
- 1 week to work
ToolsUpdate tools with the changesBooks delivered Nov 16
- 1 week to work
Books delivered Nov 30
- 1 week to work
Books delivered Dec 14
- 1 week to work
ExBIs informed om coming releaseInformed Nov 16Informed Nov 30Informed Dec 14
CETTL distributes books and give to content creatorsBooks delivered Nov 16
- 1 week to work, then release Nov 23
Books delivered Nov 30
- 1 week to work, then release Dec 07
Books delivered Dec 14
- 1 week to work, then release Dec 21
PRNews message with release
(draft release notes, find a time-slot, coordinate platforms, etc)
Release Nov 24Release Dec 08Release Dec 22
AdministratorsUpload books to download pagesRelease Nov 24Release Dec 08Release Dec 22












It's not a case we decided to publish such a table, it's to give you a glimpse on our working schedule and methodology.

Nonetheless, always remember that the mentioned dates are to be considered "Expected", meaning delays can occur.

Keep an eye on the Army Subforums, your friendly ACS staff will soon release some tasty news!